Schedule


ACTIVITYDATEDELIVERABLE
REGISTRATION  
Competition Launch8 October 2019 
Deadline for Competition Submissions4 November 2019Entry Form
Requirements Freeze4 November 2019 
PROJECT START - RESEARCH & DESIGN PHASE  
Preliminary Design Review (PDR) Deadline15 December 2019PDR Report
PDR Feedback26 January 2020 
beeApp Webinar Workshop with Open Cosmos2-6 March 2020 
Critical Design Review (CDR) Deadline5 April 2020CDR Report
Teams Receive RIDs Feedback27 April 2020 
Teams to Make Necessary Amendments4 May 2020 
CDR Reviewer/Mentor MeetingBefore 11 May 2020 
BUILD & TEST PHASE  
Delivery of beeKits to Best 5 Teams18 May 2020 
beeKit Webinar Workshop with Open Cosmos18-23 May 2020 
Competition Grant Deadline31 May 2020 
Test Readiness Review (TRR)19 July 2020TRR Report
Competition Challenge Day2 August 2020